Office moves rarely fail on the day. They fail eleven months earlier, when a notice deadline passes or the fibre order goes in late. Here is the timeline that avoids both.

Moving an office looks like a logistics problem: crates, vans and a weekend of unpacking. In practice the move day is the easy part. The real work sits in the months before, and the expensive mistakes happen early: a break-clause notice served a week late, a fibre circuit ordered after the fit-out has started, or a reinstatement bill nobody budgeted for. A timeline that starts with your current lease, not your new one, prevents most of them.

This guide sets out a nine-to-twelve-month plan for a typical small or medium office, with the lease, IT, people and budget workstreams that run alongside it. Larger moves with complex fit-outs often need longer. Everything here is general information; your lease and local law decide the actual deadlines, so have a lawyer confirm them.

Start with your current lease

Before you look at a single building, pull out your existing lease and find the dates that control your options. Missing one can lock you into another term or leave you paying for two offices at once.

  • Expiry and break dates. When does the lease end, and is there a break option before then? Break clauses usually require written notice by a fixed date, in a particular form, served on the right party at the right address.
  • Break conditions. In the UK and Ireland, breaks are often conditional, for example on rent being paid up to date or the premises being returned with vacant possession. Courts tend to apply these conditions strictly, so a small failure can invalidate the break. Read the wording with your lawyer.
  • Renewal options. If you want to keep the option of staying, note the window for exercising any renewal right. Often it closes many months before expiry.
  • Statutory notices. In England and Wales, some business leases carry security of tenure under the Landlord and Tenant Act 1954, which has its own notice procedures and timeframes. Other countries have their own rules on how commercial leases end.
  • Holding over. If you stay past expiry without agreement, North American leases commonly charge holdover rent at a steep premium to the passing rent. Know the cost before you rely on a few extra weeks.

Your current landlord is also your first negotiating counterparty. A credible search gives you leverage on renewal terms, which our guide to negotiating office rent covers.

The timeline at a glance

WhenLease and propertyIT, people and operations
12–10 months outConfirm lease deadlines; decide stay or go; appoint a tenant rep; set budget; define requirementsName an internal move lead; survey how staff use the current office; map where people commute from
10–8 monthsMarket search, tours and test fits; issue requests for proposals, including to your current landlordAudit IT and telecoms contracts and their notice periods; list equipment to move, replace or dispose of
8–6 monthsNegotiate heads of terms; lawyers draft and agree the lease; serve break or termination notice on the old spaceBrief a fit-out designer; agree layout and workplace standards; begin early staff communication
6–5 monthsSign the lease; obtain landlord and building approvals for the fit-out; tender the fit-out contractOrder fibre and internet circuits; confirm the carrier's access route into the building; order furniture with long lead times
5–2 monthsFit-out construction; regular site meetings; commission a dilapidations or restoration survey on the old spaceNetwork cabling, comms room, Wi-Fi survey, access control, security and AV installation; tender removals firms
2–1 monthsPractical completion inspections; occupancy and fire sign-offs; agree the reinstatement scope or settlement with the old landlordTest circuits and systems; issue packing instructions; update address with suppliers, banks, regulators and insurers
Move weekBuilding access and lift bookings confirmed for both buildings; protection for floors and lifts in placePack, label and move; IT team reconnects and tests over the weekend; welcome pack and floor guides ready
After the moveSnagging or punch-list items fixed; reinstatement works at the old space; hand back keys; recover depositCollect staff feedback; cancel old services; confirm number porting and mail redirection are working

Dilapidations and reinstatement

When you leave, the lease almost always requires you to hand the premises back in a specified condition. In the UK and Ireland this is called dilapidations: the landlord serves a schedule listing repairs, redecoration and the removal of your alterations, and claims the cost. In England and Wales, a landlord's damages for disrepair are generally limited to the loss in value of its interest, which is one reason claims are often negotiated down. In North America the same ground is covered by surrender, restoration or removal clauses, which may require you to strip out partitions, remove cabling and return the space to its original layout.

How to manage it:

  • Read the repair, decoration, alterations and yield-up clauses early, together with any licences for alterations you signed during the lease.
  • Find any schedule of condition recorded when you moved in. It may limit what you have to put right.
  • Commission a survey of the likely liability five or six months out, so the figure is in your budget.
  • Talk to the landlord. If they plan to refurbish, or the next tenant wants your fit-out, a cash settlement or a waiver may cost both sides less than doing the works.
  • In your new lease, negotiate limits on reinstatement now, so the next move is cheaper.

IT and telecoms lead times

IT is the workstream most often started too late. A new dedicated fibre circuit can take from several weeks to several months, particularly if the carrier needs to bring new cabling into the building, dig in the street or secure an access agreement with the landlord (called a wayleave in the UK). Order as soon as the lease is signed, and confirm early that your preferred carriers already serve the building.

  • Connectivity: primary and backup circuits from different carriers if you can, and a temporary connection in case the main circuit is late.
  • Comms room: secure, ventilated and, if it holds active equipment, cooled. Check whether the building allows supplementary cooling and backup power.
  • Cabling and Wi-Fi: a survey of the fitted space before handover, not after the desks are in.
  • Telephony: number porting can take weeks; schedule it for the move date.
  • Security and access: access cards integrated with the building's system, CCTV and visitor management.
  • Contracts: notice periods on your current internet, phone, printer leases and service contracts, so they end when you leave rather than months later.

Need office, retail or coworking space in downtown New York?

Tell us size, budget and timing. We'll connect you with up to three tenant-side brokers or space providers, usually paid by the landlord, not you.

Find space, free

Telling your team

People worry about a move long before the boxes arrive, and they fill silence with rumour. Communicate early and repeatedly.

  • Before the lease is signed: tell staff a search is under way and what you are optimising for, without naming buildings that may fall through.
  • Once it is signed: announce the location, the timing and why it was chosen. Share a commute map and the transit options; our city pages, from Toronto to Sydney, describe how staff typically get downtown.
  • During the fit-out: share the layout, desk-booking approach and what will change about how people work. Where possible, involve a few staff in choosing furniture and settings.
  • Move month: packing instructions, a timetable, who to ask, and a welcome pack covering access, lifts, bike storage, nearby food and the neighbourhood.

Check employment contracts for place-of-work or mobility clauses, and take advice on whether the move triggers any consultation duties where you operate. For staff who are relocating personally, our guide to relocating downtown for a job is a useful thing to share.

Budget lines to include

CategoryTypical lines
New spaceDeposit or guarantee, legal fees, agent fees where you pay them, rent overlap with the old office, fit-out net of any landlord contribution, design and project management fees, permits
Furniture and equipmentDesks, chairs, storage, meeting-room furniture, kitchen equipment, AV, signage
IT and telecomsCircuit installation, cabling, network equipment, Wi-Fi, access control, telephony, temporary connectivity
The moveRemovals, crates, IT disconnection and reconnection, secure document destruction, disposal or donation of old furniture, out-of-hours lift and building charges
Old spaceDilapidations or reinstatement works or settlement, final service charges or operating cost reconciliation, utilities until handback
PeopleCommunication materials, welcome packs, any commuting support, overtime for the move team
ContingencyA reserve for the overruns that every fit-out and move produces

Estimate the removals element with the moving cost tool, and use our guide to how much office space you need to make sure the new space is the right size before you start paying for it. If you are working with a broker, tenant rep brokers explained sets out what they should handle in this timeline.

Questions people ask

How far in advance should I plan an office move?

For a small or medium office, start nine to twelve months before you need to be in, and earlier if your current lease has a break clause or renewal option with a notice deadline. Large moves with a full fit-out often start 18 months or more ahead.

What are dilapidations?

Dilapidations is the UK and Irish term for a tenant's liability, at the end of a lease, to repair, redecorate and reinstate the premises as the lease requires. North American leases cover the same ground through surrender and restoration clauses. The cost can be significant, so read the clauses and get a survey early.

How long does it take to install internet in a new office?

A new dedicated fibre circuit can take anywhere from several weeks to several months, especially if the carrier needs new cabling into the building or the landlord's permission for access. Order it as soon as the lease is signed and arrange a temporary connection as a fallback.

Do I need to consult employees about an office move?

It depends on the country and on employment contracts. Many contracts include a place-of-work or mobility clause, and in some jurisdictions a move that significantly changes commutes can trigger consultation obligations. Take employment advice early and tell staff as soon as plans are firm.

Found this useful?

Down.Town is independent and free to read. Reader support funds new city guides, contests and prizes.

Support Down.Town
Free, every Friday

The Downtown Dispatch

A city centre worth your weekend, a tool or guide for movers and business owners, open contest calls and new space on the market. Pick the editions you want; leave with one click.

Editions